At “Electric Networks of Armenia” CJSC, design works have commenced across six separate lots, implemented by four companies

October 08,2025 21:08

At “Electric Networks of Armenia” CJSC, design works have commenced across six separate lots, implemented by four companies selected as winners to provide design services for the Company’s needs. Meanwhile, the procurement process aimed at engaging new companies for the delegation of construction works through a competitive tender procedure will be launched today.

To select contracting organizations for the implementation of technological connections for new consumers across the Republic of Armenia, reducing electricity losses, and carrying out power supply works planned under special programs, “ENA” CJSC has today launched an inclusive, open, and transparent quotation process comprising a total of seven lots.

According to the results of the first phase, 20 companies have expressed interest in participating in the tender process. In the next phase, technical specifications will be provided to the companies that have confirmed their intention to participate, enabling them to submit their price offers. Upon completion of the second phase, the main tender process will officially commence.
The contractor organizations performing electricity supply works for “ENA” CJSC will carry out the processes under the following seven lots:

Lot 1 – Tavush region (“Aghstev” branch), Shirak region (“Ghars” branch), Lori region (“Debed” branch), Kotayk and Gegharkunik regions (“Geghama” branch), excluding the “Charentsavan” and “Hrazdan” electrical networks.
Lot 2 – Kotayk region: “Nairi” electrical network, “Charentsavan” electrical network.
Lot 3 – Kotayk region: “Abovyan” operational district, “Hrazdan” electrical network.
Lot 4 – Ararat and Vayots Dzor regions (“Araks” branch), Syunik region (“Tatev” branch).
Lot 5 – Armavir and Aragatsotn regions (“Musalerr” branch).
Lot 6 – Yerevan city: “Nork,” “Arabkir,” and “Kentron” operational districts.
Lot 7 – Yerevan city: “Mashtots,” “Erebuni,” and “Shengavit” operational districts.

It should be noted that previously, four contracting companies carried out the works with six brigades. From now on, the same scope of construction and installation works will be performed by seven contracting companies, selected through a competitive tender process, employing a total of 28 brigades — aiming to complete new subscriber connection processes within more controlled and timely schedules.

Based on the directive of the Temporary Head of “ENA” CJSC, Romanos Petrosyan, and as a result of comprehensive studies and analyses conducted by the relevant divisions of the Company’s Technical Directorate, as of October 8 of this year, there are 276 applications at the design stage of connection works for new consumers (both individuals and legal entities) with contractual deadline violations, specifically:

“Volios” CJSC – delays in 265 connection applications.
“Energatstsnakhagits” CJSC – delays in 11 connection applications.

As of today, among the four contracting companies currently implementing new subscriber connections, approximately 600 applications have been identified with contractual delays, including:

“Cascade Energo Service” LLC – 112 delayed applications.
“Arev Construction” CJSC – 206 delayed applications.
“Luys Energy” CJSC – 106 delayed applications.
“Inteco Energo” CJSC – 175 delayed applications.

Following the instruction of the Temporary Head of “ENA” CJSC, the relevant divisions of the Company’s Technical Directorate are currently engaged in intensive collaboration with the contracting companies to accelerate the implementation of works subject to mutual obligations and deadlines stipulated in the active contracts.

We express our sincere appreciation to our citizens for their understanding and patience regarding the connection timelines under the current circumstances.

Public Relations and Media Department

“Electric Networks of Armenia” CJSC

Media can quote materials of Aravot.am with hyperlink to the certain material quoted. The hyperlink should be placed on the first passage of the text.

Comments (0)

Leave a Reply

Calendar
October 2025
Mon Tue Wed Thu Fri Sat Sun
« Sep    
 12345
6789101112
13141516171819
20212223242526
2728293031